Shortly after Victory Unlimited Construction opened in 2010, the company received its first job from SRAM to build a 70,000 square-foot building with a 10,000 square-foot mezzanine for Zipp Speed Weaponry on the Northwest side of Indianapolis. This project included the building of an office and manufacturing/distribution center for carbon performance wheels. Construction began in May 2010 and was completed in October 2010.
As part of the project, Victory Unlimited Construction also built in:
- A 26-foot clearance height.
- A 4,000-amp, 480/277-volt, three-phase electrical service.
- A 45-millimeter, mechanically-fastened TPO roof system.
- Four dock doors.
- Construction completed in six months.